The following steps
and implementation procedures are designed to
give the ISP who wishes to plunge into the telecom business an idea of
the processes and procedures necessary to become a CLEC (Competitive Local Exchange Carrier).
These procedures also give you an
opportunity to understand how much time and effort we put into your turn-key
solution.
PHASE I:
Hire a good telecom consulting firm such as ISG-Telecom Consultants
Make a determination whether becoming a "switchless reseller" CLEC or a
"facility-based" CLEC is best for your overall business plan
Analyze the current ISP financial picture and telecom costs. Have a business case
model done by ISG-Telecom, which will be utilized as the cost justification tool in order
to determine whether "facility-based" CLEC status is right for you.
Plan your strategy session
with the
ISG-Telecom team of experts (principles, regulatory and project management personnel).
This will help determine the pricing and service elements that will be set into your
tariff.
ISG-Telecom will draft your CLEC application
ISG-Telecom will draft your tariff
ISG-Telecom will begin negotiations for your interconnections agreement (or resale
agreement)
All documents are approved by client and sent to the appropriate Public Service
Commission Repeat steps V through VIII if client wishes to sell long distance services as an
IXC
PHASE II:
ISG-Telecom will contact its Strategic Partners and begin organizing equipment
layout and quotes
Eqipment is ordered
Follow-up with the PUC on certification process
ISG-Telecom starts setting up the back office procedures (Billing, customer
service, operator services, DA & 911)
Certification is received
Equipment is delivered, installed and turned-up for Beta testing
Back office functions are put in beta to co-ordinate with switch
Hire and train your sales, operations, marketing, & product marketing teams
Reseller Implementation Process
-
File with Public Utility Commission for Competitive
Local Exchange status
-
File and obtain operating codes needed
-
File and obtain Interconnection/Resale Agreement
with Incumbent Local Exchange Carrier of choice
-
Establish wholesale account with ILEC
-
Schedule provision and billing training with ILEC or
qualified trainer
-
OSS Setup including all Vendors.
-
Kickoff test and marketing strategy
Facilities-Based Implementation Process
-
File with PSC for CLEC status
-
Select and rank target cities and LATA(s)
-
Identify and define local rate structure, determine
total of NXX codes per LATA
-
Identify possible site locations for ( Customer )
central offices
-
Identify space needs for (1) switch, (2) transport
facilities, (3) power & battery plant, (4) emergency
generator plant
-
File for ILEC Interconnect Agreement
-
Review franchise/right of way requirements for each
CO location
-
Identify ILEC tandem locations within the designated
LATA(s)
-
Identify all independent tandem locations within the
designated LATA(s)
-
Identify all other Tandem functions and locations
where OS, DA, interLATA toll
-
and interexchange access is provided
CLEC status obtained
-
Identify any interconnection or collocation sites
and develop preliminary network architecture.
-
Identify primary interconnection point for
interconnection to ILEC and the public network
-
Develop a preliminary estimate of total lines,
prefixes, numbers, CCS/MS and traffic distribution
and growth rate. Estimate the switch size based on
these assumptions
-
Identify any Virtual Number Groups required in the
serving LATA and central office interconnection for
these number groups
-
Preliminary estimate of facility types and trunk
group identification for each (CLEC) central office.
-
Develop an initial demand and facilities chart based
on assumptions made above. This chart will be used
until it can be updated with actual traffic
measurements
-
Identify and initiate a meeting with ILEC Account
Manager(s)
-
Formally advise the ILEC, in writing, on the
collocation method(s) and central office locations
and request a response on availability and cost.
Provide ILEC a tentative collocation equipment
layout and floor plan for each location. Meet with
ILEC engineers to resolve any problems and to answer
questions on wiring, interfacing and other details
Interconnect agreement finalized
with ILEC(s)
-
Obtain franchise agreements with each serving city
-
ILEC begins interconnection construction
-
Request NXX codes from the network number
administrator ( LOCKHEED ).
-
66 days are required to update the LERG ( Local
Exchange Rate Group )
-
Obtain CLLI codes for the CLEC central office(s)
-
Obtain OCN code
-
Select an SS-7 provider for transporting calls
-
Identify preliminary E911 and PSAP requirements
-
Identify any special taxing arrangements for local
franchise or E911 service tax
-
Finalize the network facilities and trunking
architecture
-
CLEC begins construction at collocation sites
-
Issue ASR(s) to ILEC for trunks and establish due
dates for completion.
CLEC NPA-NXX activation date
-
Complete agreements with E911 PSAPs
-
Issue ASR(s) and establish due dates for SS-7 "A"
links. NOTE: SS-7 "A" links must be functional
before trunk testing can begin
-
Determine the database access through the SS-7
provider. This will include LIDB, 800 and LNP
-
Decide on the method of updating the LNP database
-
Obtain an SS-7 certification with the SS-7 provider
-
Issue ASR(s) for OC-X, DS3 and DS1 and establish due
dates for facilities between the ILEC and CLEC
central offices
-
ILEC and CLEC interconnect facilities and begin
acceptance testing
-
Joint testing between CLEC and ILEC of facilities
and routing
-
Joint testing between ILEC and CLEC of facilities
and routing
-
Perform LNP testing with the LNP database provider,
SS-7 provider and the ILEC
-
Establish a joint task force with the ILEC to
develop OSS interfaces for order entry,
provisioning, maintenance and trouble reports
-
Decide on how to handle Operator calls
-
Decide on how to handle billing issues
-
Establish a joint task force with the ILEC to
develop billing interfaces for exchange of billing
data.
-
The same arrangement must be established with Long
Distance service carriers (IXC)
-
Create test billing tape for CLEC central office
-
Perform billing verification with ILEC and IXC
-
Decide on how to handle Yellow Page and Directory
listings, information and distribution. Work with
ILEC Account Manager
-
Establish target date for switch activation and turn
up to network